Rehabilitation of a 30 kV / 10 kV primary electrical substation
Sonelgaz Distribution
Refurbishment of the MV equipment, power workshops and remote control of a primary substation, carried out while maintaining continuity of service.
Projects carried out for Sonelgaz Distribution, often on live substations, without interrupting supply to customers.
Sonelgaz Distribution
Refurbishment of the MV equipment, power workshops and remote control of a primary substation, carried out while maintaining continuity of service.
Sonelgaz Distribution
Construction of a new primary substation with two MV voltage levels, from civil works to electrical equipment.
Sonelgaz Distribution
Relocation of the cables of 38 MV feeders with continuity of service, and construction of 680 linear metres of cable trench.
Sonelgaz Distribution
Replacement of Sepam 2000 relays with optimised Sepam 80 relays, in six steps and without modifying the existing wiring: the old relay is disconnected and removed, the Sepam 80 is fitted into the original cut-out, then the original connectors are plugged back in and the relay is tested on site by injection.
C264 RTU, time synchronisation master, redundant switches, HMI and remote control gateway, Sepam 80 relays connected via IEC 61850 over fibre optics.